Projects

 

BAM Construction – Ryecroft School, Droylsden

Contract Value - £ 2.1 million

Type of work – SFS, Ceilings & partitions, plastering

Contract duration  – 11 months










 

BAM Construction – Chorlton High School

Contract Value - £ 1.6 million

Type of work –Ceilings & partitions, plastering, firestopping

Contract duration  – 9 months

Vinci Construction – Christie Hospital, Macclesfield

Contract Value - £ 800,000

Type of work –SFS, Ceilings & partitions, plastering, firestopping

Contract duration  – 8 months












 

Galliford Try Construction – Salford Bevan 

Contract Value - £ 550,000

Type of work –SFS, Ceilings & partitions, plastering, firestopping

Contract duration  – 6 months

Eric Wright – Broughton House

Contract Value – £1.0 million

Type of work – SFS, Ceilings & partitions, firestopping, plastering

Contract duration  –  11 months












 

Rowlinson – Bowes Street, Manchester

Contract Value – £1.3 million

Type of work – SFS, Ceilings & partitions, plastering

Contract Duration – 12 months

Cruden Construction – Manchester Health Academy

Contract Value – £680,000

Type of work – SFS, Trespa cladding, Ceilings & partitions, plastering

Contract duration  – 11 months












 

De Trafford – City Gardens, Manchester

Contract Value – £1.8 million

Type of work –  Ceilings & partitions, plastering, firestopping

Contract duration  –  Approx. 16 months